25 October 2013 pls let me know the contrac costing formulas for work.completed and percentage. and for estimated contrac also and the payment made accordingly to contractor

28 October 2013 PARAMETERS OF TRANSFERING AMOUNT TO P & L ACCOUNT ON THE BASIS OF WORK CERTIFIED

% of work certified to date

(1)<25%
(2)25-50%


(3)50% or more

(4) near completion stage
Amount to be transferred to p & L a/c

Nil
1/3*notional profit*cash received/work certified
2/3*notional profit*cash received/work certified

(a)estimated profit*work certified/contract price
(b) estimated profit*work certified/contract price*cash received/work certified
(C) estimated profit *cash received /work certified* cost of contract to date/total estimated cost

Further,
Notional profit=value of work certified+ cost of work uncertified-cost of contract to date
Estimated profit=total contract price- total estimated cost
Total estimated cost=cost of contract to date + estimated additional cost+ provision for contingencies

% of work certified= value of work certified/total contract price*100


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now


CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries



CCI Pro
Meet our CAclubindia PRO Members

Follow us
add to google news



Answer Query



Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 19 March 2026
Article Assistant

Gupta Sachdeva & Co. Chartered Accountants

New Delhi

CA Final

View Details
Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details