Query of as 16 borrowing cost

This query is : Resolved 

05 December 2014 as a statutory audtor how would you deal with the followng
abc ltd commenced construction of a flyover in mumbai in jan 2004 under BOLT scheme .
The same was completed in Feb 2005. Due to sesonal heavy rans in july 2004 n the area,the work on the flyover had to be suspended for 1 month. The company suspended the borrrowing cost of Rs 12.50 lakhs for that month from capitalisaton.

05 December 2014 it will not be capitalised as it was temporary suspension and suspension not part of project.


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now


CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries



CCI Pro
Meet our CAclubindia PRO Members

Follow us
add to google news



Answer Query



Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details