Cpm & pert use of dummy activity.

This query is : Resolved 

17 December 2014 Sir/Madam,
I want to know how to know that we have to use dummy activities in CPM & PERT Network Construction. Moreover which side the arrow should be? Are here and specific rules that govern dummy activities. I tried learning via module but i could not understand ow and when to use a dummy. Plz Help.

Thanks in advance

18 December 2014 Dummies are used in the following cases:

a. To avoid duplicating activities between 2 nodes.
b. To correct dangling errors.
c. To indicate the logical sequence of he activities.

Arrow will be normally in the same direction as flow of activity. However, this is not a hard and fast rule since network diagrams shapes vary from case to case even for the same problem.

Best way to learn is to practice Network diagrams in large numbers. There is no substitute to this.

Thanks!


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now


CCI Pro

Similar Resolved Queries


loading


Unanswered Queries



CCI Pro
Meet our CAclubindia PRO Members

Follow us
add to google news



Answer Query



Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details
Company
Featured ARTICLESHIP 19 March 2026
Article Assistant

Gupta Sachdeva & Co. Chartered Accountants

New Delhi

CA Final

View Details
Company
Featured 14 March 2026
Associate CA

N N V Satish&co

Hyderabad

CA

View Details