Cpm & pert use of dummy activity.

This query is : Resolved 

17 December 2014 Sir/Madam,
I want to know how to know that we have to use dummy activities in CPM & PERT Network Construction. Moreover which side the arrow should be? Are here and specific rules that govern dummy activities. I tried learning via module but i could not understand ow and when to use a dummy. Plz Help.

Thanks in advance

18 December 2014 Dummies are used in the following cases:

a. To avoid duplicating activities between 2 nodes.
b. To correct dangling errors.
c. To indicate the logical sequence of he activities.

Arrow will be normally in the same direction as flow of activity. However, this is not a hard and fast rule since network diagrams shapes vary from case to case even for the same problem.

Best way to learn is to practice Network diagrams in large numbers. There is no substitute to this.

Thanks!


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now


CCI Pro

Similar Resolved Queries


loading


Unanswered Queries



CCI Pro
Meet our CAclubindia PRO Members

Follow us
add to google news



Answer Query



Company
19 May 2026
Fundraising Expert

MentorsWorld Ventures Private Limited

Ahmedabad

Others

View Details
Company
ARTICLESHIP 17 May 2026
CA Article /Trainee

Malik Sunil & co

New Delhi

CA Foundation

View Details
Company
22 May 2026
Sr. Financial Analyst - Consolidation

Search Synergy

Mumbai

CA

View Details
Company
08 May 2026
CHARTERED ACCOUNTANT

SHAH LADHA AND ASSOCIATE

Ahmedabad

CA

View Details
Company
23 May 2026
Account Executive

SMJ global advisors pvt ltd

New Delhi

B.Com

View Details
Company
ARTICLESHIP 04 June 2026
Article

Rakhecha & Co.

New Delhi

CA Inter

View Details
Company
26 May 2026
Audit executive

vdsr & co LLP

Chennai

CA Inter

View Details
Company
11 May 2026
Post office

Post office

Anakapalle

Others

View Details