Work in progress or unbilled revenue


This query is : Resolved 

Avatar

Querist : Anonymous

Profile Image
Querist : Anonymous (Querist)
24 December 2009 Can someone pls tell me how they calculate/estimate work-in-progress or unbilled revenue as per the requirement of As-7, for software development companies?

Contracts are both T&M and Fixed contracts.

25 December 2009 As per AS-7 First you need to calculate the Percentage of completion of contract i.e cost incurred up to date/ total budgeted cost fo the project x 100

then you have to apply the percentage of completion on the contract value you can get the proportion value of sales related cost incurred

now you calculate

Unbilled Revenue=Actual sales - The sales proportion to the budget cost which you arrived based on the percentage of completion



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
15 October 2026
Senior Accountant

Continental Belting Pvt Ltd

Mumbai

B.Com

View Details
Company
06 October 2026
Assistant Manager - Audit and Compliance

Ravi K Jain & Co

Noida

Others

View Details
Company
ARTICLESHIP 30 September 2026
CA Article Assistant

CA Suraj Garg & Associates

New Delhi

CA Final

View Details
Company
14 October 2026
Accountant

Rize.farm

Bengaluru

B.Com

View Details
Company
12 October 2026
Chartered Accountant - Internal Audit

HKC | Chartered Accountants & Business Advisors

Ludhiana

CA

View Details
Company
05 October 2026
Senior Accountant

Vision IT Peripherals Pvt Ltd

Mumbai

B.Com

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details
Company
ARTICLESHIP 01 October 2026
Articled Assistant

KPSN & Associates LLP

Chennai

CA Inter

View Details