A contractor received a work order before July 2022, with GST at 12%. Payment and GSTR3B filing also occurred at 12% after July 2022. However, the department has issued a notice demanding the difference of 6% GST, plus interest and penalty, citing Notification 3/2022 which increased the rate to 18% for construction work after July 2022. The contractor is seeking advice on how to proceed.
11 July 2025
I am a contractor i got the work order before july 2022 and recieved the payment after july 2022 the department paid me tax @ 12% and i also paid the gst through gstr3b @12% now i recived a notice from department asking me to pay tax @18% What should i do now
13 July 2025
Sir the gst paid to me after july 2022 was 12% but the gst department is asking me to pay 18% As i have already paid with 12% they are asking to pay remaining 6% with interest and penalty
13 July 2025
Sir as per notification 3/2022 dated 13/07/22 the rate for construction work was changed from 12% to 18% But I received the work order before july 2022 in which the gst rate was 12% but the gstr7 filed by department was after july 2022 I paid the gst as per work order as i recived the tax @12% Now i recived a notice asking me to pay @ 18% as per notification 03/2022