costing contract a/cs

This query is : Resolved 

04 April 2009 dear sir/ madam


D ltd took a contract for 5lakhs on 01/07/2006. on 30th june when a/cs were closed the following details about the contract were gathered.material:Rs 1,00,000 wages:Rs50,000 gen expences: Rs10,000 materials on hand 30/6/2007 :Rs 25,000 work certified:Rs 2,00,000 cash received :Rs1,50,000 work certified:Rs15,000 depreciation:Rs 5000 and the contract has escalation clause "inthe event of prices of materials and rates of wages increase by morethan 5% the contract price will be inreased accordingly by 25% of the rise in the cost of materials and wages beyond 5%in each case. It was found that since the date of signing the agreement the prices of materials and wage rates increased by 25% the value of the work certified doesnot take into a/c the affect of he above clause. is this is the problem plese explain me about the escalation clause
thanking u
praveena

05 April 2009 Praveena,
Your problem is not clear.
1. "the information as on 31/6/2007" - What is this information?
- Is it estimated Cost given at the time of submitting quotation?

2. When the Co "took a contract for 5lakhs on 01/07/2006".
- was it relevant to declare "materials on hand 30/6/2007"?
Sorry I am unable to give you any reply. pl clarify the same if I misunderstood.
Welcome.
S. Banerjee


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now


CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries



CCI Pro
Meet our CAclubindia PRO Members

Follow us
add to google news



Answer Query