Costing process


This query is : Resolved 

03 October 2012 Hi All,

please suggest the Process which i need to follow process costing or Job costing.

we are manufacturers of Tipper and Mixer bodies. we have five process
1. Metal forming
2. Body fabrication
3. painting
5. Assembly
4. Quality & inspection
we prepare all parts individual and do assembly the parts final.

03 October 2012 process costing is followed where output of one process is the input for the next process. Dependent activities as is called under PERT/CPM. (Programme evaluation and review technique / Critical path method)The wording suggest that the activities are dependent in a sequence and hence process costing can be made good use of.

03 October 2012 me too in similiar industry, & doing costing work.. both can be employed, but for better results job costing should be adopted... bcoz it gives you analysis order/job wise & stock can also be maintained.


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
ARTICLESHIP 07 November 2026
Article Assisstant

DPV & Associates

Chennai

CA Inter

View Details
Company
23 October 2026
Sr. Accountant

SANKARAN & KRISHNAN

New Delhi

B.Com

View Details
Company
Featured 29 October 2026
Accounts Executive

Synergy Keystone

Chennai

B.Com

View Details
Company
30 October 2026
Asst Manager Accounts

Goodwin Pumps India Pvt Ltd

Chengalpattu

CA Inter

View Details
Company
13 November 2026
Accountant

New Mobile India

Muzaffarpur

B.Com

View Details
Company
Featured 27 October 2026
semi-qualified CA

Saini Pati Shah & Co LLP, Chartered Accountants

Mumbai

CA Final

View Details
Company
12 November 2026
Tax Product Specialist

BharatX.ai

Gurgaon

B.Com

View Details
Company
24 October 2026
CA Industrial Trainee

Fytomax Nutrition Private Limited

Aurangabad

CA Inter

View Details