Costing process


This query is : Resolved 

03 October 2012 Hi All,

please suggest the Process which i need to follow process costing or Job costing.

we are manufacturers of Tipper and Mixer bodies. we have five process
1. Metal forming
2. Body fabrication
3. painting
5. Assembly
4. Quality & inspection
we prepare all parts individual and do assembly the parts final.

03 October 2012 process costing is followed where output of one process is the input for the next process. Dependent activities as is called under PERT/CPM. (Programme evaluation and review technique / Critical path method)The wording suggest that the activities are dependent in a sequence and hence process costing can be made good use of.

03 October 2012 me too in similiar industry, & doing costing work.. both can be employed, but for better results job costing should be adopted... bcoz it gives you analysis order/job wise & stock can also be maintained.


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
ARTICLESHIP 28 September 2026
Junior Accountant

J S P M & Associates LLP

Pune

B.Com

View Details
Company
19 September 2026
CA/Semi-CA/BCom

Pravin Sarvaiya

Mumbai

CA Inter

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details
Company
26 September 2026
Chartered Accountant

pushpganga ventures

Pune

CA

View Details
Company
13 October 2026
Accountant

Zerdi & Co. Chartered Accountants

Pune

B.Com

View Details
Company
14 October 2026
Accountant

Rize.farm

Bengaluru

B.Com

View Details
Company
08 October 2026
Accounts and Tax Associate

POOJA R TELI & CO

Pune

CA Inter

View Details
Company
ARTICLESHIP 17 October 2026
Articled Assistant

RRPM & Associates LLP

Chennai

CA Inter

View Details