Our company engaged in property developement. Right now we have only one residential project. We started the construction 3 years back. Expenses incurred upto last FY 10-11- shown as WIP in balance Sheet.
FY 11-12 we started booking and got advance from some customers. it will take another 2 years to complete the project.
07 May 2012
AS-7 is applicable to contractors engaged in construction activities. Generally, a developer is not treated as a contractor. . Developers may engage contractors to perform the construction work and AS-7 applies to such contractors. . In other words In a case where developer has not entered into a construction contract with other parties (land owners), and carrying on own construction, AS-7, will not apply. .
Querist :
Anonymous
Querist :
Anonymous
(Querist)
08 May 2012
Thanks for valuable advise, One more doubt amount lying WIP should written off after completion of the project only?