Accounting of of Interest Cost paid on original claim by contractor -arbitration award/ court order

This query is : Resolved 

16 August 2021 It is informed that , arbitration award/ court order in respect of a claim by contractor has been passed in favour of the contractor in respect of capital works and such arbitration award/ court order has been challenged in a court of law/ higher court, the amount of arbitration award/ court order (including interest till the date of award, if any) becomes the claim amount for the purpose of maintenance of Register of Claims .

Pl advice whether interest till the date of award on the amount of arbitration award/ court order is capitalised or not.

16 August 2021 Such interest can be capitalised till the completion of the capital works.


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro

Follow us
add to google news


Answer Query



Company
24 June 2026
Senior Account (VA Client Operations)

Karbon Business

Bengaluru

CA Inter

View Details
Company
Featured 16 July 2026
CA Inter, CA Intermediate, CA IPCC, CA CPT , CA SemiQualifie

Vakilsearch.com

Chennai

CA Inter

View Details
Company
ARTICLESHIP 16 July 2026
Article Assistant

G A R U D & Associates

New Delhi

CA Inter

View Details
Company
24 June 2026
Chartered Accountant

CA Darshita Shah & Co

Nadiad

CA

View Details
Company
ARTICLESHIP 27 June 2026
CA Articled Trainee And Paid Assistant

SKAA & Associates

New Delhi

CA Inter

View Details
Company
ARTICLESHIP 27 June 2026
Article

SNCO

Mumbai

CA Inter

View Details
Company
06 July 2026
Accountant

Agarwal Anoop and Associates

Noida

CA Final

View Details
Company
06 July 2026
Chartered Accountant (Indirect Taxation)

Gowra Ventures Pvt Ltd

Hyderabad

CA

View Details