16 August 2021 It is informed that , arbitration award/ court order in respect of a claim by contractor has been passed in favour of the contractor in respect of capital works and such arbitration award/ court order has been challenged in a court of law/ higher court, the amount of arbitration award/ court order (including interest till the date of award, if any) becomes the claim amount for the purpose of maintenance of Register of Claims .

Pl advice whether interest till the date of award on the amount of arbitration award/ court order is capitalised or not.

16 August 2021 Such interest can be capitalised till the completion of the capital works.