Accounting of of Interest Cost paid on original claim by contractor -arbitration award/ court order


This query is : Resolved 

16 August 2021 It is informed that , arbitration award/ court order in respect of a claim by contractor has been passed in favour of the contractor in respect of capital works and such arbitration award/ court order has been challenged in a court of law/ higher court, the amount of arbitration award/ court order (including interest till the date of award, if any) becomes the claim amount for the purpose of maintenance of Register of Claims .

Pl advice whether interest till the date of award on the amount of arbitration award/ court order is capitalised or not.

16 August 2021 Such interest can be capitalised till the completion of the capital works.


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
04 September 2026
CA inter Or ca finalist

A Jaiswal and company

Lucknow

CA Final

View Details
Company
28 August 2026
Audit Manager

K A R M & CO

Mumbai

CMA

View Details
Company
ARTICLESHIP 17 August 2026
Article Assistant

K R Kiran Kumar & Associates

Bengaluru

CA Inter

View Details
Company
ARTICLESHIP 25 August 2026
CA Article's

Saini Pati Shah & Co LLP

Mumbai

CA Inter

View Details
Company
Featured 11 September 2026
Audit Executive

RBSM Corporate Advisors Private Limited

Pune

CA

View Details
Company
ARTICLESHIP 07 September 2026
CA Articles

Kothari Jain Patil & Chartered Accountants

Pune

CA Inter

View Details
Company
21 August 2026
Accountant

A G International

Kolkata

B.Com

View Details
Company
27 August 2026
ACCOUNTANT

CHARUPREETI & CO

Noida

Graduate (Any)

View Details