Booking of Exp more than Income


This query is : Resolved 

22 May 2009 Dear Friends,
Our company is Project Based Company.
We have taken a project.
We have given the whole contact to a sub contractor.
we have issued a Sale Bill of Rs. 6 Crore on our client.
The sub contractor has issued a bill of Rs. 7 Crore for the same project.
Can we book the whole Rs. 7 Crore Exp in the F Y 2008-09 or shoule we defer Rs. 1 Crore to next F Y?
The Project will be completed in the F Y 2010-11 & we are expecting overall profit from this.

22 May 2009 As per AS-7 construction contracts you have to recognise the profit based on percentage completion method, actual receipts and payments does not have any implications

22 May 2009 Yes i agree with the expert.

07 June 2011 Yes Manikanta is right


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
ARTICLESHIP 25 August 2026
CA Article's

Saini Pati Shah & Co LLP

Mumbai

CA Inter

View Details
Company
ARTICLESHIP 29 August 2026
Article Assistant

RRPM & ASSOCIATES LLP

Chennai

CA Inter

View Details
Company
ARTICLESHIP 07 September 2026
Article/ Paid Assistant

Murali and Sumeet Chartered Accountant

Bengaluru

CA Foundation

View Details
Company
ARTICLESHIP 01 September 2026
Articles

Saini Pati Shah & Co LLP, Chartered Accountants

Mumbai

CA Foundation

View Details
Company
28 August 2026
Assistant Manager

NRS AND ASSOCIATES

Kozhikode

CA Inter

View Details
Company
ARTICLESHIP 16 September 2026
Article Assistant

MANUJ SHARMA AND COMPANY

Noida

CA Inter

View Details
Company
ARTICLESHIP 26 August 2026
Article Assistant

ANIVESH CONSULTANTS LLP

Gurgaon

CA Inter

View Details
Company
ARTICLESHIP 04 September 2026
Accounts Executive

Hema Yashwanth & Associates

Chennai

B.Com

View Details