Standard Output in 12 hrs is 48
Actual output in 12 hrs is 42
Time Rate @ 7.50 per hour
According to the emerson plan if the efficiency is more than 662/3 to 100%, A bonus increasing from 0.01% to 20% above basic wages on 100% efficiency.
In the text book, it has been calcuated that the bonus efficiency percentage is 7.56 in case of 87% of efficiency, but no idea how they have calcuated the same.
Plzz Help me