Help ca final ama

Final 644 views 4 replies

Can ne1 tell me how the question of PERT (Q.4) solved in the RTP May 13 CA Final AMA

Thnx in advance

Replies (4)

hii nikita

its nothing but its told about creashing the activities 

so

dont go for this method but go for your method or clas method so you will understand properly.

so do it own your way

 

 

It is a resource smoothing Problem, where by a time scaled diagram needs to be drawn, for evaluating the resource allocation optimally. 

Thanks for your replies. Sathish I don't hv ne idea about resource smoothening. It would be nice if you could explain further.

Bhavik I don't know how should I proceed as I could not find the relevant data for solving through crashing. What is the data given in table about labourers???

hii,

no its not labourers.

some is asking about to rearrange the activity by taking in to mind labour as well as carpenters, so we ave to focus on activities that how we can reduce labourer as well as carpenters.