Hi all,

Please clarify whether Marketing expenses incurred for a particular project can be considered direct costs for calculation of percentage completion method as per AS 7.

Replies (1)

No. Marketing expenses (or selling expenses) cannot be considered as part of direct cost. Para 19 of AS-7 reads as under:

 
"Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:
(a) general administration costs for which reimbursement is not specified in the contract;
(b) selling costs;
(c) research and development costs for which reimbursement is not specified in the contract; and
(d) depreciation of idle plant and equipment that is not used on a particular contract"
 
 
Point (b) explicitly excludes selling costs from direct cost / contract related costs and hence should not be considered for percentage of completion

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 27 October 2026
semi-qualified CA

Saini Pati Shah & Co LLP, Chartered Accountants

Mumbai

CA Final

View Details
Company
05 October 2026
Senior Accountant

Vision IT Peripherals Pvt Ltd

Mumbai

B.Com

View Details
Company
08 October 2026
SALES TELECALLER

HIRE NOVA

Lucknow

Graduate (Any)

View Details
Company
14 October 2026
Accountant

Rize.farm

Bengaluru

B.Com

View Details
Company
ARTICLESHIP 17 October 2026
Articled Assistant

RRPM & Associates LLP

Chennai

CA Inter

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details
Company
31 October 2026
Accountants

sankaran and krishnan

New Delhi

B.Com

View Details
Company
ARTICLESHIP 20 October 2026
CA ARTICLE

AMKN & CO

Noida

CA Inter

View Details