Construction contracts

Hi all,

Please clarify whether Marketing expenses incurred for a particular project can be considered direct costs for calculation of percentage completion method as per AS 7.

Replies (1)

No. Marketing expenses (or selling expenses) cannot be considered as part of direct cost. Para 19 of AS-7 reads as under:

 
"Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:
(a) general administration costs for which reimbursement is not specified in the contract;
(b) selling costs;
(c) research and development costs for which reimbursement is not specified in the contract; and
(d) depreciation of idle plant and equipment that is not used on a particular contract"
 
 
Point (b) explicitly excludes selling costs from direct cost / contract related costs and hence should not be considered for percentage of completion

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
09 September 2026
SENIOR AUDITOR & ACCOUNTS MANAGER

Anupam Parashar & Co.

Ghaziabad

CA Final

View Details
Company
19 September 2026
Finance Manager

Mugdha Art Studio

Hyderabad

CA

View Details
Company
08 September 2026
Semi-Qualified Assitant

Subrahmanyam & Sivudu CA Firm

Hyderabad

CA Inter

View Details
Company
30 September 2026
Senior Accounts Executive

Codeboard Technology

Chennai

MBA

View Details
Company
22 September 2026
Account Assistant

Chirag P Shah & Co. Chartered Accountant

Pune

B.Com

View Details
Company
ARTICLESHIP 21 September 2026
CA Article Assistant

KK & Company Chartered Accountant

Pune

CA Inter

View Details
Company
ARTICLESHIP 30 September 2026
CA Article Assistant

CA Suraj Garg & Associates

New Delhi

CA Final

View Details
Company
ARTICLESHIP 07 September 2026
Article/ Paid Assistant

Murali and Sumeet Chartered Accountant

Bengaluru

CA Foundation

View Details