Construction contracts

749 views 1 replies

Hi all,

Please clarify whether Marketing expenses incurred for a particular project can be considered direct costs for calculation of percentage completion method as per AS 7.

Replies (1)

No. Marketing expenses (or selling expenses) cannot be considered as part of direct cost. Para 19 of AS-7 reads as under:

 
"Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:
(a) general administration costs for which reimbursement is not specified in the contract;
(b) selling costs;
(c) research and development costs for which reimbursement is not specified in the contract; and
(d) depreciation of idle plant and equipment that is not used on a particular contract"
 
 
Point (b) explicitly excludes selling costs from direct cost / contract related costs and hence should not be considered for percentage of completion


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
26 May 2026
CA / MBA (Finance) / CMA / M.Com (Finance)

Sri Aurobindo Gnostic Centre of Education

New Delhi

CA

View Details
Company
09 June 2026
Accounts Associate

S Madan and CO

New Delhi

Graduate (Any)

View Details
Company
23 May 2026
Article Assistant

Geeta Manchanda & CO.

New Delhi

CA Inter

View Details
Company
26 May 2026
Education Content Creator

Adyayam Education LLP

Bengaluru

CA Foundation

View Details
Company
ARTICLESHIP 27 May 2026
CA Article Trainee

Rahul Dang & Associates-Chartered Accountants

Pune

CA Inter

View Details
Company
04 June 2026
Semi Qualified CA

Goyal Puneet & Associates

New Delhi

CA Final

View Details
Company
Featured 27 May 2026
Lead Conversion Executive / Sales Closing Executive

SMJ global advisors pvt ltd

New Delhi

B.Com

View Details
Company
ARTICLESHIP 28 May 2026
Accounts, Audit & Compliance Executive

Shyam Joshi & Associates

Pune

B.Com

View Details