AS 735 views 1 replies

Hi all,

Please clarify whether Marketing expenses incurred for a particular project can be considered direct costs for calculation of percentage completion method as per AS 7.

Replies (1)

No. Marketing expenses (or selling expenses) cannot be considered as part of direct cost. Para 19 of AS-7 reads as under:

 
"Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:
(a) general administration costs for which reimbursement is not specified in the contract;
(b) selling costs;
(c) research and development costs for which reimbursement is not specified in the contract; and
(d) depreciation of idle plant and equipment that is not used on a particular contract"
 
 
Point (b) explicitly excludes selling costs from direct cost / contract related costs and hence should not be considered for percentage of completion


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details
Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details