Plz Help me wid regards to a costing problem

I m unable to get the correct answer of a problem of Costing--LearningCurve

I hv attached d file containing problem along wid solution


Attached File : 446540 724924 problem 19.doc downloaded: 131 times
Replies (1)

Dear Mr. Yogesh

First thing is that you had done calculation mistake in computing overtime days and exact days are 7.375 days, plz check it out and the second thing is that penalty shall be levied for whole machine and not for part of machine and exact penalty amt. is Rs. 80000 instead of Rs. 52000.

Leave a Reply

Your are not logged in . Please login to post replies