mind twister

10 people do the job in 10 hours = the job needs 100 man-hours

15 people do the job in 5 hours = the job needs 75 man-hours

 

This is contradictory. There is something amiss here. Do give clarification. 

1st case- The portion of work performed by 10 people in 1 hour = 1/10 part of work

2nd case- The portion of work done by 15 people in 1 hour = 1/5 part of work

therefore, 25 people can do the part of work in 1 hour = 1/10 + 1/5 = 3/10 par of work

so, total time taken by 25 people to complete the task = 10/3 hour = 3 hours and 20 min = 200 min

The work will be completed by 3.75 hours i.e. 3 hours and 45 minutes...

3 hours & 20 mins..

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
09 September 2026
Chartered Accountant

Aviv Global Private Limited

Ahmedabad

CA

View Details
Company
08 September 2026
Audit Executive

Thammana & Associates

Srikakulam

B.Com

View Details
Company
29 August 2026
Chartered Accountant

Velionit Consulting PVT LTd

Mumbai

CA

View Details
Company
28 August 2026
Audit Manager

K A R M & CO

Mumbai

CMA

View Details
Company
ARTICLESHIP 04 September 2026
Accounts Executive

Hema Yashwanth & Associates

Chennai

B.Com

View Details
Company
09 September 2026
SENIOR AUDITOR & ACCOUNTS MANAGER

Anupam Parashar & Co.

Ghaziabad

CA Final

View Details
Company
Featured 21 September 2026
Consultant - Reporting

Finrep Advisors LLP

Mumbai

CA

View Details
Company
28 August 2026
Assistant Manager

NRS AND ASSOCIATES

Kozhikode

CA Inter

View Details