Contract Costing Query

Q1. the cost incuures upto 31.03.2001 was as under:

                              In Lakhs (Rs.)

D.Material             280

D.Labour              100

OH                          60

erection cost to date    110

the contract price is 11 crore and cash received is 6 crore. a technical estimates of the contract indicate the following degree of completion of work:

D. material 70%

D.Labour and OH 60%

Erection 40%

you are required to etimate the profit that could be taken to profit and loss a/c against  this partly completed contract as at 31.03.2001

 

please help!!!!!!!!!!!

Replies (1)

please see the attechment page no 19 to 21 your solution is there

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
19 October 2026
Accountant

Jari Saree Center

New Delhi

Others

View Details
Company
30 September 2026
Senior Accounts Executive

Codeboard Technology

Chennai

MBA

View Details
Company
ARTICLESHIP 07 October 2026
Article assistant

S.K.Bajpai & Co.

Noida

B.Com

View Details
Company
08 October 2026
SALES TELECALLER

HIRE NOVA

Lucknow

Graduate (Any)

View Details
Company
ARTICLESHIP 01 October 2026
Articled Assistant

KPSN & Associates LLP

Chennai

CA Inter

View Details
Company
08 October 2026
Account Executive

Elite Taxation

New Delhi

CA Foundation

View Details
Company
ARTICLESHIP 28 September 2026
Junior Accountant

J S P M & Associates LLP

Pune

B.Com

View Details
Company
10 October 2026
Accounts Associate Level 1

Abic and Mani Chartered Accountants

Kottayam

B.Com

View Details