Contract Costing Query

IPCC 479 views 1 replies

Q1. the cost incuures upto 31.03.2001 was as under:

                              In Lakhs (Rs.)

D.Material             280

D.Labour              100

OH                          60

erection cost to date    110

the contract price is 11 crore and cash received is 6 crore. a technical estimates of the contract indicate the following degree of completion of work:

D. material 70%

D.Labour and OH 60%

Erection 40%

you are required to etimate the profit that could be taken to profit and loss a/c against  this partly completed contract as at 31.03.2001

 

please help!!!!!!!!!!!

Replies (1)

please see the attechment page no 19 to 21 your solution is there


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
03 May 2026
Senior Chartered Accountant

Nirmal Jain & Co

New Delhi

CA

View Details
Company
ARTICLESHIP 05 May 2026
ARTICLED ASSISTANT

JS ADVISORS

New Delhi

CA Inter

View Details
Company
ARTICLESHIP 23 May 2026
Article Assistants

Acupro Consulting

Gurgaon

CA Inter

View Details
Company
14 May 2026
Senior Accounts Executive

Karan Gupta & Co.

New Delhi

Graduate (Any)

View Details
Company
26 May 2026
Senior Accountant cum purchase Manager

Vardhaman Group of India

Pimpri Chinchwad

CA Inter

View Details
Company
ARTICLESHIP 30 April 2026
Article Assistant

J SINGH & ASSOCIATES

Ahmedabad

CA Inter

View Details
Company
22 May 2026
Audit assistant

Displayandbeyond

Mumbai

CA

View Details
Company
08 May 2026
CHARTERED ACCOUNTANT

SHAH LADHA AND ASSOCIATE

Ahmedabad

CA

View Details