Contract Costing Query

Q1. the cost incuures upto 31.03.2001 was as under:

                              In Lakhs (Rs.)

D.Material             280

D.Labour              100

OH                          60

erection cost to date    110

the contract price is 11 crore and cash received is 6 crore. a technical estimates of the contract indicate the following degree of completion of work:

D. material 70%

D.Labour and OH 60%

Erection 40%

you are required to etimate the profit that could be taken to profit and loss a/c against  this partly completed contract as at 31.03.2001

 

please help!!!!!!!!!!!

Replies (1)

please see the attechment page no 19 to 21 your solution is there

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
14 October 2026
Accountant

Rize.farm

Bengaluru

B.Com

View Details
Company
21 October 2026
CA INTER/ BCOM WITH EXPERIENCE

CA S KUMAR GUPTA & CO

Amritsar

CA Inter

View Details
Company
08 October 2026
SALES TELECALLER

HIRE NOVA

Lucknow

Graduate (Any)

View Details
Company
15 October 2026
Senior Accountant

Continental Belting Pvt Ltd

Mumbai

B.Com

View Details
Company
19 October 2026
Accountant

Jari Saree Center

New Delhi

Others

View Details
Company
12 October 2026
Chartered Accountant - Internal Audit

HKC | Chartered Accountants & Business Advisors

Ludhiana

CA

View Details
Company
14 October 2026
GST & TDS ASSISTANT

AGGARWAL SANJAY & ASSOCIATES

New Delhi

B.Com

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details