Contract Costing Query

IPCC 485 views 1 replies

Q1. the cost incuures upto 31.03.2001 was as under:

                              In Lakhs (Rs.)

D.Material             280

D.Labour              100

OH                          60

erection cost to date    110

the contract price is 11 crore and cash received is 6 crore. a technical estimates of the contract indicate the following degree of completion of work:

D. material 70%

D.Labour and OH 60%

Erection 40%

you are required to etimate the profit that could be taken to profit and loss a/c against  this partly completed contract as at 31.03.2001

 

please help!!!!!!!!!!!

Replies (1)

please see the attechment page no 19 to 21 your solution is there


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
29 May 2026
Company Secretary - Part time

Shaswat initial support private limited

Ahmedabad

CS

View Details
Company
04 June 2026
Semi Qualified CA

Goyal Puneet & Associates

New Delhi

CA Final

View Details
Company
22 May 2026
U.S. Financial Reporting & Consolidation Manager

Karia Overseas

Ahmedabad

CA

View Details
Company
Featured 27 May 2026
Lead Conversion Executive / Sales Closing Executive

SMJ global advisors pvt ltd

New Delhi

B.Com

View Details
Company
01 June 2026
Audit, Taxation & Compliance Executive

R P S K & Associates

Nashik

CA Inter

View Details
Company
Featured 27 May 2026
Lead Conversion Executive / Sales Closing Executive

SMJ global advisors pvt ltd

New Delhi

B.Com

View Details
Company
29 May 2026
Finance Head

Bhawar Sales Corporation

Chennai

Graduate (Any)

View Details
Company
26 May 2026
CA / MBA (Finance) / CMA / M.Com (Finance)

Sri Aurobindo Gnostic Centre of Education

New Delhi

CA

View Details