Everything is clear in the solution. Contract price is 20L and 50 % has been certified so work certified is 10L
| Originally posted by : SANDEEP R. WAWHAL | ||
![]() |
friends, pls explain how work certified and notional profit is calculated in the attached question. Urgent |
![]() |
Dear SANDEEP,
Work Certified is already given in the question as certified by architect i.e, 50% of contract price of Rs.20 Lakhs
Work Uncertified is calculated on cost basis, As given in the question that 2/3 of contract was completed and 1/2 half was certifed by the architect, means 2/3-1/2 = 1/6 remains uncertified.
Work Cost for 2/3 of contract is 10,49,000, therefore value of uncertified work will be
1049000 X 3/2 X 1/6 = 2,62,250
Notional profit is balancing figure or may be calculated like this
Work Certified- (Work Cost- Work Uncertified)= Notional Profit
10,00,000-(10,49,000-2,62,500) = 2,13,250
Hope this will clear you doubt,
Thanks prabhakar for detailed explainaiton......
Agree with friend Prabhakar............
Mistake sir.....
Contract revenue should be 20lac * 66.67% =1333400
Profit (1333400-1049000)=284400
In contract costing,which price is considered for degree of completion whether the contract price or the contractee accepted price?
As the cost to date is 1049000, and here it given that 2/3 of contract is completed it means, cost of full contract will be 1049000*3/2=1573500. And it's given 50% of contract is completed than it means cost of work certified will be 50% of 1573500 i,.e 786750. So notional profit= work certified - cost of work certified i.e, 1000000-786750=213250 Work uncertified(valued at cost)= cost to date(works cost)- cost of work uncertified i,e. 1049000-786750=262250...
AT CONTRACT PRICE AT COST
CONTRACT COMPLETED UP TO DATE 13,33,333 (2/3 X 2000000) 10,49,000
WORK CERTIFIED UP TO DATE 10,00,000 (1/2 X 20,00,000) ? (786750)
(1049000 X 1000000) 1333333
WORK UNCERTIFIED AT COST = 1049000 -- 786750 = 262250
AT CONTRACT PRICE AT COST
CONTRACT COMPLETED UP TO DATE 13,33,333 (2/3 X 20,00,000) 10,49,000
WORK CERTIFIED UP TO DATE 10,00,000 (1/2 X 20,00,000) ? (7,86,750)
(10,00,000 X 10,49,000)/13,33,333
WORK UNCERTIFIED AT COST = 1049000 -- 786750 = 262250
ADD ALL EXPENSEES IN DR. AND LESS RALIVENT ITEMS THEN GOT 10,49,000
Sir,
How to find the amount 10,49,000/-
Your are not logged in . Please login to post replies
Click here to Login / Register
Subrahmanyam & Sivudu CA Firm
Hyderabad
CA Inter
View Details
RBSM Corporate Advisors Private Limited
Pune
CA
View Details
CCI
Pro
India's largest network for
finance professionals