EXPLORING VARIABLE OVERHEAD VARIANCES: A good manager will want to explore the nature of variances relating to variable overhead. It is not sufficient to simply conclude that more or less was spent than intended. As with direct material and direct labor, it is possible that the prices paid for underlying components deviated from expectations (a variable overhead spending variance). On the other hand, it is possible that the company's productive efficiency drove the variances (a variable overhead efficiency variance). Thus, the Total Variable Overhead Variance can be divided into a Variable Overhead Spending Variance and a Variable Overhead Efficiency Variance.
Before looking closer at these variances, it is first necessary to recall that overhead is usually applied based on a predetermined rate, such as $X per direct labor hour (you may find it helpful to review this concept from Chapter 19). This means that the amount debited to work in process is driven by the overhead application approach. This will become clearer with the following illustration.
AN ILLUSTRATION OF VARIABLE OVERHEAD VARIANCES: Let's return to the illustration for Blue Rail. Variable factory overhead for August consisted primarily of indirect materials (welding rods, grinding disks, paint, etc.), indirect labor (inspector time, shop foreman, etc.), and other items. Extensive budgeting and analysis had been performed, and it was estimated that variable factory overhead should be applied at $10 per direct labor hour. During August, $105,000 was actually spent on variable factory overhead items. The standard cost for August's production was as follows:

The total variable overhead variance is unfavorable $3,000 ($102,000 - $105,000). This may lead to the conclusion that performance is about on track. But, a closer look reveals that overhead spending was quite favorable, while overhead efficiency was not so good. Remember that 12,500 hours were actually worked. Since variable overhead is consumed at the presumed rate of $10 per hour, this means that $125,000 of variable overhead (actual hours X standard rate) was attributable to the output achieved. Comparing this figure ($125,000) to the standard cost ($102,000) reveals an unfavorable variable overhead efficiency variance of $23,000. However, this inefficiency was significantly offset by the $20,000 favorable variable overhead spending variance ($105,000 vs. $125,000). The following diagram may prove useful in helping you sort out the variable overhead variances:

JOURNAL ENTRY FOR VARIABLE OVERHEAD VARIANCES: The following journal entry can be used to apply variable factory overhead to production and record the related variances:
| 8-31-XX |
Work in Process Inventory
|
|
102,000
|
|
| |
Variable Overhead Efficiency Variance |
|
23,000
|
|
| |
Variable OH Spending Variance |
|
|
20,000
|
| |
Factory Overhead
|
|
|
105,000
|
| |
To increase work in process for the standard variable overhead, and record the related efficiency and spending variances |
|
|
|
CAREFUL INTERPRETATION OF VARIABLE OVERHEAD VARIANCES: Material and labor variances are more easily interpreted than variable overhead variances. The variable overhead efficiency variance can be somewhat confusing because it may reflect efficiencies or inefficiencies experienced with the base used to apply overhead, rather than overhead itself. For Blue Rail, remember that the total number of hours was "run up" beyond plan because of inexperienced labor. A good manager will want to keenly evaluate the cause and meaning of variable overhead variances. In fact, the variances are likely only the point of beginning for a proper evaluation. Remember that variable overhead is made up of many components. For Blue Rail, it is conceivable that the inexperienced welders used more welding rods, and the welds were likely sloppier requiring more grinding to smooth out the joints. Further, it is likely that inspectors had to spend more time checking work to make sure that the welds were strong. While the overall variance calculations would provide signals about these issues, a manager would actually need to drill down into each individual cost component (perhaps calculating variances for each budgeted line item rather than just on an overall basis) to truly find areas for business improvement.
How important is control of overhead? A study of self-made 50-year old millionaires revealed very little correlation between wealth and income, and a strong correlation between wealth and life-long savings patterns. Although the study is related to individuals, the message rings equally true for business. Careful control of spending is essential to long-term value building. Businesses vary considerably in their attitudes and discipline as it relates to control of overhead. Some businesses are rather cavalier about controlling things like light/electricity usage, control over low cost parts, efficiency in shipping methods, etc. Others are rather fanatical about maintaining absolute and stringent controls. For instance, one controller of a manufacturing plant was frustrated with the number of screws that were dropped and left to be swept away at the end of each business day. These were seemingly insignificant to the employees. In frustration, the controller scattered a box of nickels onto the factory floor -- by the end of the day none remained for the janitorial staff to sweep away. A subsequent memo was issued reminding everyone that screws cost 5¢ each. The rather obvious point was to draw a comparison between the nickels that everyone was eager to recover and the screws for which there was little concern. To build a successful business, a good manager will keep a keen eye on all overhead items, and control them with vigor. The variable overhead variances are macro indicators of success in accomplishing this goal.
VARIANCES RELATING TO FIXED FACTORY OVERHEAD: Frequently (but not always), actual fixed factory overhead will show little variation from budget. This results because of the intrinsic nature of a fixed cost. For instance, rent is usually subject to a lease agreement that is relatively certain. Depreciation on factory equipment can be calculated in advance. The costs of insurance policies are negotiated and tied to a contract. Even though budget and actual numbers may differ little in the aggregate, the underlying fixed overhead variances are nevertheless worthy of close inspection.
AN ILLUSTRATION OF FIXED OVERHEAD VARIANCES: Let's take one final look at Blue Rail. Assume that the company budgeted total fixed overhead at $72,000; only $70,000 was actually spent (seemingly a good outcome). Here our accounting objective will be to allocate the $70,000 actually spent between work in process and variance accounts. The temptation would be to book $72,000 into work in process and reflect a $2,000 offsetting favorable variance -- but that would be the wrong approach!
Instead, the Work in Process account should reflect the standard fixed overhead cost for the output actually produced. We get to this calculated value by reconsidering the company's original assumptions about production. Assume that Blue Rail had planned on producing 4,000 rail systems during the month; remember that only 3,400 systems were actually produced -- output was disappointing, perhaps due to the inexperienced labor pool. This means that the planned fixed overhead was $18 per rail ($72,000/4,000 = $18). Because three labor hours are needed per rail, the fixed overhead allocation rate is $6 per direct labor hour ($18/3). Use this new information to consider the following illustration for fixed factory overhead (remember from the earlier discussion that the standard labor hours for the actual output were 10,200):

By reviewing this familiar looking illustration, you can see that $61,200 should be allocated to work in process. This reflects the standard cost allocation of fixed overhead that would be attributable to the production of 3,400 units (i.e., 10,200 hours should be used to produce 3,400 units). Notice that this differs from the budgeted amount of fixed overhead by $10,800, representing an unfavorable Fixed Overhead Volume Variance. In other words, since production did not rise to the anticipated level of 4,000 units, much of the fixed cost (that was in place to support 4,000 units of output) was "wasted" or "under-utilized." Thus, the measured volume variance is highly unfavorable. If more units had been produced than originally anticipated, the fixed overhead volume variance would be favorable (this would reflect total budgeted fixed overhead being spread over more units than originally anticipated). For Blue Rail, the volume variance is offset by the more easily understood favorable Fixed Overhead Spending Variance of $2,000; $70,000 was spent versus the budgeted $72,000. Together, the two variances combine to reveal a net $8,800 unfavorable Total Fixed Overhead Variance.
JOURNAL ENTRY FOR FIXED OVERHEAD VARIANCES: The diagram at right illustrates the flow of fixed costs into the Factory Overhead account, and on to Work in Process and the related variances. Below is a compound journal entry to apply fixed factory overhead to production and record the related variances:
| 8-31-XX |
Work in Process Inventory
|
|
61,200
|
|
| |
Fixed Overhead Volume Variance |
|
10,800
|
|
| |
Fixed OH Spending Variance |
|
|
2,000
|
| |
Factory Overhead
|
|
|
70,000
|
| |
To increase work in process for the standard fixed overhead, and record the related volume and spending variances |
|
|
|
RECAPPING STANDARDS AND VARIANCES: The foregoing provided a painstakingly detailed account of the variances for Blue Rail. Before moving on, it is best to put the entire subject in perspective. The goal is to compare standard costs to actual costs. Blue Rail's work in process is recorded at the standard costs found in the Blue circles (hint -- the work in process inventory of blue rails is recorded at the amounts found in blue circles), while actual costs are found in the red circles. These amounts are recapped in the table below:

You will notice that the standard cost of $686,800 corresponds to the amounts assigned to work in process inventory via the various journal entries, while the total variances of $32,200 were charged/credited to specific variance accounts. By so doing, the full $719,000 actually spent is fully accounted for in the records of the Blue Rail.
EXAMINING VARIANCES: Not all variances need to be analyzed. One must consider the circumstances under which the variances resulted and the materiality of amounts involved. One should also understand that not all unfavorable variances are bad. For example, buying raw materials of superior quality (at higher than anticipated prices) may be offset by reduction in waste and spoilage. Likewise, favorable variances are not always good. Blue Rail's very favorable labor rate variance resulted from using inexperienced, less expensive labor. Was this the reason for the unfavorable outcomes in efficiency and volume? Perhaps! The challenge for a good manager is to take the variance information, examine the root causes, and take necessary corrective measures to fine tune business operations.
In closing this discussion of standards and variances, be mindful that care should be taken in examining variances. If the original standards are not accurate and fair, the resulting variance signals will themselves can prove quite misleading.
BALANCED SCORECARD APPROACH TO PERFORMANCE EVALUATION
ALTERNATIVE PERFORMANCE EVALUATION TECHNIQUES: Thus far, this chapter has focused on budgets, standards, and variances to assess entity performance. However, other non-financial metrics should also be employed in performance evaluation. This is sometimes referred to as maintaining a balanced scorecard, meaning that performance assessment should take a holistic approach. Long-term business success will not be achieved if the focus is only on near-term financial outcomes. At the same time, financial goals are not abandoned; the goal is to achieve balance.
With the balanced scorecard approach, an array of performance measurements are developed. Each indicator should be congruent with the overall entity objectives. Further, each measure should be easily determined and understood. These measurements can relate to financial outcomes, customer outcomes, or business process outcomes. Although a balanced scorecard approach may include target thresholds that should be met, the primary mantra is on improvement. This means that all participants are continually striving to beat pre-existing scores for each measure.
Early in this chapter, you saw how responsibility accounting concepts caused performance reports to be prepared for different steps in the corporate ladder. This notion is equally applicable to the balanced scorecard approach. The overall corporate entity may have macro targets and measures. Similarly, sub-units will have their own unique goals. A scorecard approach can even be pushed down to the individual employee level. For instance, a retail store may require that tellers complete a certain number of transactions per hour. This "quota" in essence would represent a nonfinancial metric that can be scored for each employee.
THE BALANCED SCORECARD IN OPERATION: You saw for Blue Rail Manufacturing a number of examples of financial goals that could be included in a balanced scorecard assessment. Examples include the standard cost for material, the standard labor hours per rail set, the expected production level, and so forth. But, what would be some examples of customer outcomes and business process outcomes?