Treatment of survey cost

678 views 1 replies

Our company is planning to lay Pipeline Project for Joining 3-4 Gas wells. Rout Survey for the same was intially done 5-6 years back and till date project could not be started due to Negative FR.

 

Just want to know whether this intial survey  expenditures should be kept in CWIP(Capital Work in Prog) or should be charged Off. ( I tried to search in AS -10 but couldn't fint anything abt Survey Cost)

Thanks & Regards

anil Chauhan

Dehradun

 

Replies (1)

Dear friend, since the report was negative there was no need to capitalize it.

Now you can charge it in P& L a/c as per AS-5 fue to change in estimation as a seperate item. However, under I.T act you will not be allowed deduction of this expense now

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
25 June 2026
AUDIT MANAGER

JDAS & ASSOCIATES

New Delhi

CA

View Details
Company
ARTICLESHIP 08 June 2026
Internal & Taxation Article

O P Bagla & Co LLP

New Delhi

CA Inter

View Details
Company
25 June 2026
Accounts & Taxation Executive

Dindukurthy & Associates

Hyderabad

MBA

View Details
Company
29 May 2026
Accounts assistant

Shubh Consultancy

Mumbai

Graduate (Any)

View Details
Company
16 June 2026
Sr. Associate / Assistant Manager | TAS / FDD

Boutique Investment Bank & Transaction Advisory Firm

Gurgaon

CA

View Details
Company
22 June 2026
Finance Manager- Chartered Accountant

Triveni Turbine Limited

Bengaluru

CA

View Details
Company
29 May 2026
Company Secretary - Part time

Shaswat initial support private limited

Ahmedabad

CS

View Details
Company
ARTICLESHIP 20 June 2026
Articleship

RB KESHRI & CO

Mumbai

B.Com

View Details