Rtp ama

483 views 1 replies
q9 of nov 2014 of ama.. I have taken coaching from sanjay agarwal sir..nd as per his teaching ans should be 36160 units.. But ans given in rtp is different.. Can anyone help me in this
Replies (1)

Answer in RTP is correct.

Over/Under Absorption is always computed in comparison with Actual Overhead and not Budgeted Overheads. Thus, to get Absorbed O/H u have to first calculate Actual O/H and then add Overabsorption amount.