IN QUESTION NO. 3 (iii)OF RTP (Material costing )

annual demand =18000  UNITS  for 360 days . EOQ=3600 UNITS

 no. of order  is calculated to be 10 but acc to me it must be 5 {annual demand /EOQ}

plz clarify my doubt . thanks in advance.

Replies (4)

it should be 5 

but wait for more replies

ya it should be 5 orders

its 5 only

5..............................

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 11 September 2026
Audit Executive

RBSM Corporate Advisors Private Limited

Pune

CA

View Details
Company
08 September 2026
Audit Executive

Thammana & Associates

Srikakulam

B.Com

View Details
Company
ARTICLESHIP 16 September 2026
CA Article Trainee

SR BAGAI & Co.

New Delhi

CA Inter

View Details
Company
09 September 2026
SENIOR AUDITOR & ACCOUNTS MANAGER

Anupam Parashar & Co.

Ghaziabad

CA Final

View Details
Company
19 September 2026
Finance Manager

Mugdha Art Studio

Hyderabad

CA

View Details
Company
08 September 2026
Semi-Qualified Assitant

Subrahmanyam & Sivudu CA Firm

Hyderabad

CA Inter

View Details
Company
ARTICLESHIP 07 September 2026
CA Articles

Kothari Jain Patil & Chartered Accountants

Pune

CA Inter

View Details
Company
ARTICLESHIP 29 August 2026
Article Assistant

RRPM & ASSOCIATES LLP

Chennai

CA Inter

View Details