				Originally posted by : SANDEEP R. WAWHAL | 
		
		
			
				  | 
			
				 
				friends, 
				 
				pls explain how work certified and notional profit is calculated in the attached question. 
				 
				Urgent | 
			
				  | 
		
	
	Dear SANDEEP,
	 
	Work Certified is already given in the question as certified by architect i.e, 50% of contract price of Rs.20 Lakhs
	Work Uncertified is calculated on cost basis, As given in the question that 2/3 of contract was completed and 1/2  half was certifed by the architect, means 2/3-1/2 = 1/6 remains uncertified.
	Work Cost for 2/3 of contract is 10,49,000, therefore value of uncertified work will be
	1049000 X 3/2 X 1/6 = 2,62,250
	Notional profit is balancing figure or may be calculated like this
	 
	Work Certified- (Work Cost- Work Uncertified)= Notional Profit
	10,00,000-(10,49,000-2,62,500) = 2,13,250
	 
	Hope this will clear you doubt,