To determine profit or loss after completion, compare the project’s total revenue earned with all costs attributable to it. Include direct materials, labour, subcontracting and site expenses, plus a reasonable allocation of project-related overheads; deduct credit notes or discounts from revenue. Use the same revenue basis consistently—for example, exclude GST if it is collected on behalf of the Government.
A simple Excel layout:
| Particulars | Amount (₹) |
|---|---:|
| Contract value, excluding GST | |
| Approved variations/claims recognised | |
| Less: discounts, credit notes or penalties | |
| Net project revenue | `=B2+B3-B4` |
| Materials consumed | |
| Direct labour | |
| Subcontractor costs | |
| Equipment, freight and site expenses | |
| Allocated project overheads | |
| Other attributable costs | |
| Total project cost | `=SUM(B6:B11)` |
| Project profit/(loss) | `=B5-B12` |
| Profit/(loss) margin | `=IFERROR(B13/B5,0)` |
For a completed project, reconcile the figures to the final customer billings and actual costs, including accrued but not yet invoiced costs. Keep disputed claims or unapproved variations out of revenue unless they meet your applicable recognition criteria. The figures needed to tailor the sheet are the project’s billing basis, cost heads and overhead-allocation method.
This project close-out can feed directly into your job-costing and management-reporting workflow. Manual tracking across invoices, timesheets and site records is difficult; automation reduces repetitive work while professional judgment remains in control. At Jir AI, our 2,000+ AI agents and 650+ integrations streamline GST, ITR, TDS, TCS and other compliance workflows, helping reduce manual workload by up to 70%. For a walkthrough of workflow automation, connect with us on WhatsApp: https://wa.me/message/3HVOZ7HIY4ESC1.