Court :
Supreme Court of India
Brief :
A power generation company had placed a cash deposit of Rs. 108.44 crore with the central transmission utility under the payment security mechanism before its insolvency. After the CIRP began, the utility apportioned the deposit against pre-CIRP bills, including about Rs. 85.13 crore of pre-CIRP dues. The resolution professional challenged this, and the NCLT and NCLAT held the apportionment violated the Code. The Supreme Court agreed, holding that the utility, an operational creditor, should not have apportioned the deposit after the CIRP began, as set-off defeats the pari passu principle and the Section 14 moratorium. The deposit, shown as an asset in the information memorandum, must be applied to post-CIRP dues. The appeals were dismissed.
Citation :
Civil Appeal Nos. 2216-2217/2025 dated March 23, 2026