Court :
Supreme Court of India
Brief :
A bidder offered to buy a liquidated company's plant as a going concern, paid a commitment advance, and later sought more time from the NCLT. The NCLT extended the deadline on condition that all amounts paid would be forfeited if the revised timelines were missed. The bidder paid only part and then sought a refund. The Supreme Court held that the NCLT could impose such terms under Rule 15 of the NCLT Rules, that timelines are central to the Insolvency and Bankruptcy Code, and that a court-supervised liquidation sale is not a private contract, so Section 74 of the Contract Act does not apply. Having accepted the extension, the bidder could not challenge the forfeiture. The appeals were dismissed.
Citation :
Civil Appeal Nos. 3625-3628/2025 dated December 10, 2025