Differential Tax Amount Post-GST Not Reimbursed to Contractors

Quick Summary
The Orissa High Court has provided significant relief to contractors facing unexpected tax burdens due to the shift from VAT to GST. The court ordered the State GST department to follow its own revised guidelines for works contracts. Contractors who entered agreements before GST implementation but received payments afterwards are advised to make representations to authorities based on these guidelines.

Court :
Orissa High Court

Brief :
The Hon'ble Orissa High Court, in the case of M/s. Bhanjadeo Constructions v. State of Odisha & Others, [W.P.(C) No.38497 of 2021] granted major relief to contractors by staying the coercive steps against the contractors and ordered the State GST department to abide by its circular, Finance Department vide Office memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated December 10, 2018 to address the problems with works contracts brought on by the change from the Value-Added Tax (“VAT”) to the Goods and Services Tax (“GST”) tax system.

Citation :
FIN-CTI-TAX-0045-2017/38535/F

The Hon'ble Orissa High Court, in the case of M/s. Bhanjadeo Constructions v. State of Odisha & Others, [W.P.(C) No.38497 of 2021] granted major relief to contractors by staying the coercive steps against the contractors and ordered the State GST department to abide by its circular, Finance Department vide Office memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated December 10, 2018 to address the problems with works contracts brought on by the change from the Value-Added Tax (“VAT”) to the Goods and Services Tax (“GST”) tax system.

Facts

M/s. Bhanjadeo Constructions (“the Petitioner”) challenged the decision of Respondent to withhold payment of the differential tax amount resulting from the change in tax regime, i.e. from VAT into the GST which took place on July 1, 2017.

Issue

Whether Petitioner is liable to pay tax which they never anticipated while entering into the Contract?

Held

The High Court noted that the Odisha Government has come out with revised guidelines vide Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated December 10, 2018 (“Revised Guidelines”) related to work contract suppressing the guidelines issued vide Finance Department letter dated December 7, 2017.  The revised guidelines states that:

  • The Schedule of Rates-2014 (“Revised SoR-2014”) has been revised by the State Government vide Work Department OM No. 13827/WD in order to comply with the provisions of GST relating to work contracts. Therefore, while preparing estimates for a work after July 1, 2017, the GST exclusive work value is to be arrived at as per the revised SoR-2014 and then GST will be added at the appropriate rate.
  • In GST regime, the work contractor is required to raise Tax Invoices clearly showing the taxable work value and GST (CGST+SGST) separately.
  • In case of work, where the tender was invited before the July 01, 2017 on the basis of SoR-2014, but payment made for the balance work or full work after the implementation of GST, a procedure laid down in the revised guidelines is to be followed. 

In view of the revised guidelines issued by the State Government, the Court asked the Petitioner to make a comprehensive representation before the appropriate authority and directed the authorities that if such representation is filed then the authority shall consider and dispose the same in the light of the revised guidelines. 

In case, the Petitioner is still aggrieved by the decision of the authority, Petitioner shall have the opportunity to challenge the same before the Court. 

FAQ :

Contractors faced issues with differential tax amounts arising from the transition from the Value-Added Tax (VAT) system to the Goods and Services Tax (GST) system, particularly when payments for work were made after July 1, 2017.

The High Court ordered the State GST department to adhere to its circular of December 10, 2018, which provides guidelines for addressing problems with works contracts under the GST regime.

The revised guidelines state that for estimates prepared after July 1, 2017, the GST exclusive work value should be calculated using the revised Schedule of Rates-2014, and then GST should be added. For contracts tendered before July 1, 2017, but paid for after GST implementation, a specific procedure outlined in the revised guidelines must be followed.

Contractors are advised to make a comprehensive representation to the appropriate authority, referencing the revised guidelines. The authorities are directed to consider and dispose of these representations in light of the guidelines.

Yes, if a contractor is still aggrieved by the decision of the authority after filing a representation, they have the opportunity to challenge it before the Court.

 

Bimal Jain
Published in GST
Views : 319

Comments




CCI Pro



Company
ARTICLESHIP 07 September 2026
Article/ Paid Assistant

Murali and Sumeet Chartered Accountant

Bengaluru

CA Foundation

View Details
Company
Featured 21 September 2026
Consultant - Reporting

Finrep Advisors LLP

Mumbai

CA

View Details
Company
ARTICLESHIP 21 September 2026
CA Article Assistant

KK & Company Chartered Accountant

Pune

CA Inter

View Details
Company
ARTICLESHIP 18 September 2026
Industrial Trainee

Twenty Point Nine Five Ventures Private Limited

Noida

CA Inter

View Details
Company
30 September 2026
Senior Accountant

Codeboard Technology

Chennai

B.Com

View Details
Company
22 September 2026
Account Assistant

Chirag P Shah & Co. Chartered Accountant

Pune

B.Com

View Details
Company
19 September 2026
CA/Semi-CA/BCom

Pravin Sarvaiya

Mumbai

CA Inter

View Details
Company
Featured 12 September 2026
Assistant Manager - Finance & Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details