Querry About Costing Paper of CA Final Old Syllabus of Nov. 2019


Mamta Soni   20 November 2019

Mamta Soni

 1 likes  25 points

| My Other Post

Que No 2(a) of Costing is about the lerning Curve theory and ask for calculation hours of 5th day, 7th day and 11th day...but they have not provided log values and log table as well in exam hall. Just because of without log values we are not able to solve the problem and lose 8 marks freely. Anyone can please check there is really have any mistake in Que paper and want some solution regarding same issues.

avater

Madhu Akilesh   20 November 2019

Madhu Akilesh

 1 likes  9 points

View Profile | My Other Post

There is no need of log value, the sum can be done by applying learning rate on the labour hours average method and by hours we can multiply with per HR labour rate

avater

surendra singhavi (student)     20 November 2019

surendra singhavi
student 
 10 likes  124 points

View Profile | My Other Post

No need of log value

avater

shradha (-)     20 November 2019

shradha
- 
 2 likes  76 points

View Profile | My Other Post

But the question itself specified that each gift will be made a independent labourer. how can LC be applied if one labour is making one gift. doesn't question suggest that 1 labour was allocated for each gift? 4 labourers 4 gifts.
can anyone share the full solution?

Savita Gupta   21 November 2019

Savita Gupta

 3 likes  25 points

View Profile | My Other Post

Learning curve applies on single labour. if it was supposed to be deliver in 4 days it has to be done by 4 workers and so on.

avater

Mamta Soni   21 November 2019

Mamta Soni

 1 likes  25 points

View Profile | My Other Post

What abt 5th day, 7th day & 11th day calculation. Can anyone provide full solution of the same que

avater

Vipul Mandowara (student)     21 November 2019

Vipul Mandowara
student 
 9 likes  102 points

View Profile | My Other Post

One worker takes 76.8 hrs, that is 9.6 days. so the 11th order would be met by assigning to single labourer.

IF 7 the day then we get 7*8 equals to 56 hours. So a single labourer wouldn't be able to fullfill.
if assigned to two labourer ( two units to each) then one time leaning p.u. 24 hours. so two workers will make two units each total labour of 48 hours.
finally as we got to know that to apply one time leaning i.e two units by one worker we need minimum 48 hrs (6 days), so in five days it would be done by one worker each, no leaning effect.
it was" all work CAN be assigned to 1 labourer, not is assigned.

avater

Mamta Soni   23 November 2019

Mamta Soni

 1 likes  25 points

View Profile | My Other Post

Thnks to all of you..it make some sense

avater

Harshal Ajmera (STUDENT)     28 November 2019

Harshal Ajmera
STUDENT 
 1 likes  28 points

View Profile | My Other Post

Vipul mandowara
(ii) part of question 2(a) the 7 day of the order .
learning curve is applicable .
in that case 2 labourer will work