PERT vs CPM vs BUDGET

yasaswi gomes (My grammar is ๐Ÿ’ฏ good I)   (7290 Points)

06 July 2021  

Looks like CPM is close to Budgeting, doesnt it?

Activity Critical Path Method Budget - Deterministic method
Days Most likely (M) Actual work Completed Project cost (Days * Costs) Stage of completion %
A Purchasing material and warehousing at site


7 โœ“ 3,00,000 20%
B Bulldozing to prepare constructing foundation


3 โœ“ 50,000 3%
C Laying foundation





15 โœ“ 100000 7%
D Foundation watering time




15 โœ“ 20000 1%
E 1st tower layer





10 โœ“ 300000 20%
F 2nd tower layer





10 โœ“ 300000 20%
G Final tower layer and installing satellite equipment

12 โœ“ 400000 27%

Total Estimations





72
14,70,000 100%

Project evaluation and Review Technique (PERT) - Probability model Optimistic (O) Most likely (M) Pessimistic (P) PERT Estimates = (O+4M+P)/6 Sigma  (P-O/6) Pert variance
A Purchasing material and warehousing at site

5 7 11 24 1.0 1
B Bulldozing to prepare constructing foundation

2 3 7 4 0.8 0.7
C Laying foundation




10 15 25 17 2.5 6.3
D Foundation watering time



10 15 30 21 3.3 11.1
E 1st tower layer




7 10 20 12 2.2 4.7
F 2nd tower layer




7 10 20 12 2.2 4.7
G Final tower layer and installing satellite equipment
9 12 20 13 1.8 3.4

Total








101 14 32

STANDARD DEVIATION= 3.7 days








Probability of completing project in 102 days= 102-101/SD 0.268866






Using Z- Table, 0.27= 99.6% probability that work can be completed in 102 days 



















Probability of completing the work in 72 days= 72-101/SD -7.79713






Using Z- Table, -7.79713 = 0.832 








So, 1-0.832= 0.168 or 16.80% probability that work will be completed in 72 days