Transfer Pricing Page No 7.30    Of PM.               How to come 1,50,000 mtr at 80% level and 2,50,000 at 100  % level 

Replies (2)
Attached
500000 mtr is total production capacity of textile. out of which 30% it sells to process department which means 150000. and 50% to outside. total 400000 mtrs sold by textile department. 20% of production capacity is untilised.

at 100 % capacity utilisation 50% for outsider and 30%+20% extra for process department i.e 150000+ 100000= 250000 mtr

at 80% capacity textile department is selling only 30% of 500000
at 100% capacity textile department is selling 50% of 500000


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details