RERA QUESTIONS

when project cost is 1000 builder invested till date 400 and booking advances recieved 100 in RERA Account construction work completed 40 percent
How much amount builder withdrawal from rera account? can builder withdraw above 30 percent from above rupees 100 for personal use?
Replies (1)

70% Amount should be utilised for Project Construction. Rest 30% promoters can utilised for personal use.

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
ARTICLESHIP 18 September 2026
Industrial Trainee

Twenty Point Nine Five Ventures Private Limited

Noida

CA Inter

View Details
Company
15 October 2026
Senior Accountant

Continental Belting Pvt Ltd

Mumbai

B.Com

View Details
Company
08 October 2026
SALES TELECALLER

HIRE NOVA

Lucknow

Graduate (Any)

View Details
Company
26 September 2026
Chartered Accountant

pushpganga ventures

Pune

CA

View Details
Company
ARTICLESHIP 07 October 2026
Article Trainee/ CMA Trainee

RMA And Associates LLP

New Delhi

CA Inter

View Details
Company
ARTICLESHIP 21 September 2026
CA Article Assistant

KK & Company Chartered Accountant

Pune

CA Inter

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details
Company
ARTICLESHIP 08 October 2026
ARTICLE TRAINEE

S.B.G. & CO. CHARTERED ACCOUNTANTS

New Delhi

CA Inter

View Details