Costing Paper -PERT/CPM question

Hello everyone,
Question 2(b) of pert cpm has given tm on the 3rd column while solving the question two Critical line comes to 20.
Whether someone has also faced it??
Replies (8)

can you give the question

No..It is 26 Week...
No..It is 26 Week...
yes but refer question to is not last column
if you ignore it answer will be 26
please solve again...it come to 26 Week..
yes I have faced the same issue and wasted precious time during exam
yes me and my 3 friend face same issue..

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
17 September 2026
Chartered Accountant

Dass Gupta & Associates

Gurgaon

CA

View Details
Company
ARTICLESHIP 15 September 2026
Freelance Taxation Content Writer Intern

Interactive Media Pvt Ltd.

New Delhi

CA Inter

View Details
Company
08 October 2026
Accounts and Tax Associate

POOJA R TELI & CO

Pune

CA Inter

View Details
Company
30 September 2026
Senior Accounts Executive

Codeboard Technology

Chennai

MBA

View Details
Company
19 September 2026
Finance Manager

Mugdha Art Studio

Hyderabad

CA

View Details
Company
ARTICLESHIP 01 October 2026
Articled Assistant

KPSN & Associates LLP

Chennai

CA Inter

View Details
Company
16 September 2026
Internal Audit - Team Lead

Consulting & Beyond

Chennai

CA

View Details
Company
Featured 03 October 2026
Accountant

A P Lodha and Associates

Jalna

B.Com

View Details