Somebody please let me know whether "plant returned to site" will be credited to the Contract Account or not..

Replies (1)

Hello, laugh

Think of Contract Account as a personal account.

As a contractor, when you are giving the material to the contract: 

Contract account: Personal: Debit the receiver.
Material account: Asset: Credit what goes out.

  • Contract Account Dr.
    To, Material issued Cr.

Similarly, As a contractor, when you are getting back the material from the contract:

Material: Asset: Debit what comes in.
Contract: Personal: Credit the giver.

  • Material/Plant returned to site Dr
    To, Contract A/c Cr

Therefore in Contract A/c,

By, Plant returned to site. yes

Regards,
Subhash. 

 