Contract costing

I WANT 2 KNOW WHT IS THE DIFFRENCE B/W COST OF WORK CERTIFIED & VALUE OF WORK CERTIFIED.

THNX IN ADVANCE.

Replies (4)

Work certified is that portion of the contract which is completed and for which certification is received from either Architect or Surveyor.  Work certified is always valued at Contract Price.

Value of work certified is that part of work certified for which Cash has been received from the  Contractee.Generally 80% of work certified is paid by the Contractee, and 20% is kept as Retention Money.(This 80%,20% is in the case where Question Remains Silent.).

 

the difference between the two is simply THE PROFIT on the work CERTIFIED...that is it...

agree with dheeraj  cost of work certified + notional profit ))= value of wc 

THNX A LOT DHEERAJ,PREM & MRIDUL.

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
08 October 2026
Account Executive

Elite Taxation

New Delhi

CA Foundation

View Details
Company
12 October 2026
Chartered Accountant - Internal Audit

HKC | Chartered Accountants & Business Advisors

Ludhiana

CA

View Details
Company
Featured 21 September 2026
Consultant - Reporting

Finrep Advisors LLP

Mumbai

CA

View Details
Company
08 October 2026
Accounts and Tax Associate

POOJA R TELI & CO

Pune

CA Inter

View Details
Company
14 October 2026
GST & TDS ASSISTANT

AGGARWAL SANJAY & ASSOCIATES

New Delhi

B.Com

View Details
Company
19 September 2026
CA/Semi-CA/BCom

Pravin Sarvaiya

Mumbai

CA Inter

View Details
Company
10 October 2026
Accounts Associate Level 1

Abic and Mani Chartered Accountants

Kottayam

B.Com

View Details
Company
30 September 2026
Senior Accountant

Codeboard Technology

Chennai

B.Com

View Details