Contract costing

I WANT 2 KNOW WHT IS THE DIFFRENCE B/W COST OF WORK CERTIFIED & VALUE OF WORK CERTIFIED.

THNX IN ADVANCE.

Replies (4)

Work certified is that portion of the contract which is completed and for which certification is received from either Architect or Surveyor.  Work certified is always valued at Contract Price.

Value of work certified is that part of work certified for which Cash has been received from the  Contractee.Generally 80% of work certified is paid by the Contractee, and 20% is kept as Retention Money.(This 80%,20% is in the case where Question Remains Silent.).

 

the difference between the two is simply THE PROFIT on the work CERTIFIED...that is it...

agree with dheeraj  cost of work certified + notional profit ))= value of wc 

THNX A LOT DHEERAJ,PREM & MRIDUL.

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
15 October 2026
Senior Accountant

Continental Belting Pvt Ltd

Mumbai

B.Com

View Details
Company
02 November 2026
Audit Executive

SRJP & Co LLP

Kochi

CA Inter

View Details
Company
ARTICLESHIP 17 October 2026
Articled Assistant

RRPM & Associates LLP

Chennai

CA Inter

View Details
Company
14 October 2026
GST & TDS ASSISTANT

AGGARWAL SANJAY & ASSOCIATES

New Delhi

B.Com

View Details
Company
14 October 2026
Asst. Manager/Dy Manager (Costing)

manufacturing

Pune

CMA

View Details
Company
24 October 2026
CA Industrial Trainee

Fytomax Nutrition Private Limited

Aurangabad

CA Inter

View Details
Company
ARTICLESHIP 20 October 2026
CA ARTICLE

AMKN & CO

Noida

CA Inter

View Details
Company
Featured 07 November 2026
Chartered Accountant

DPV & Associates

Chennai

CA

View Details