I WANT 2 KNOW WHT IS THE DIFFRENCE B/W COST OF WORK CERTIFIED & VALUE OF WORK CERTIFIED.

THNX IN ADVANCE.

Replies (4)

Work certified is that portion of the contract which is completed and for which certification is received from either Architect or Surveyor.  Work certified is always valued at Contract Price.

Value of work certified is that part of work certified for which Cash has been received from the  Contractee.Generally 80% of work certified is paid by the Contractee, and 20% is kept as Retention Money.(This 80%,20% is in the case where Question Remains Silent.).

 

the difference between the two is simply THE PROFIT on the work CERTIFIED...that is it...

agree with dheeraj  cost of work certified + notional profit ))= value of wc 

THNX A LOT DHEERAJ,PREM & MRIDUL.

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
ARTICLESHIP 01 September 2026
Article Assistant

SGNG & Associates

New Delhi

CA Inter

View Details
Company
ARTICLESHIP 17 August 2026
Article Assistant

K R Kiran Kumar & Associates

Bengaluru

CA Inter

View Details
Company
27 August 2026
ACCOUNTANT

CHARUPREETI & CO

Noida

Graduate (Any)

View Details
Company
ARTICLESHIP 14 August 2026
Article Assistant

N J Suresh & Associates

Bengaluru

CA Inter

View Details
Company
21 August 2026
Accountant

A G International

Kolkata

B.Com

View Details
Company
21 August 2026
Finance Manager

Resollect Technologies Pvt Ltd

Mumbai

CA

View Details
Company
04 September 2026
CA inter Or ca finalist

A Jaiswal and company

Lucknow

CA Final

View Details
Company
18 August 2026
CA Semi Qualifies

Goyanka and Associates

New Delhi

CA Inter

View Details