Construction contract

767 views 3 replies

x ltd. undertook a contarct to contract a building for rs.3 cr. on 1st sep,11 . on 31st march,12 the co. found that it had already spent  rs. 1 cr 80 lakhs on the constrution . prudent estimate of additional cost for completion was rs 1 cr. 40 lakh. . what amt should be charged , to revenue in the final accounts for the year ended on 31st, 2012 , as per the provisions of accounting stndrd 7 " constution contract revised" ???

in this i m not abl?e to find the degree of completion..??/

Replies (3)

Degree of Completion= work done upto the date/Total Estimated cost for the Project*100

1.80Cr/3.2Cr*100=56.25%

Revenue should be recognised in the Books =3cr*56.25=1.6875Cr

Loss 1.8cr-1.6875Cr=0.1125Lakhs

can u plz xplain me how u got 3.2 cr 

 

@ sreenath can you explain what you have done

As per my opinion:-

If in the year end of 31st mar 2012 there is a notional profit(i.e. cr. balance in contract a/c ) and expected loss at end of contract (i.e. contract price 3cr and total expences is 3.2cr) then you shoul not recognized any profit just make only contingency reserve

sreenath

Read more at: /forum/construction-contract-224718.asp#.UIH8T1GUL6s


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details
Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details