Program Evaluation and Review Technique
Q.4. A project consisting of thirteen activities having duration and resource requirements
shown below:
Activity Duration (days) Labourers required
A 2 2L
B 4 2C,2L
C 4 4C
D 3 2L
E 4 6C
F 7 2L
G 2 4C
H 5 4C,2L
I 2 2C
J 5 2C
K 2 2L
L 3 4L
M 2 4L
* L stands for labourers and C stands for carpenters

Analyse the project from the point of view of resources and to bring out the necessary steps
involved in the analysis and smoothing of resources.