As - 7 plz. help me

688 views 3 replies
Contract price is Rs. 5.6 lakhs cost incurred to date is Rs. 5 lakhs work certified is Rs. 4.2 lakhs work uncertified is Rs. 2 thousands further cost to complete 2 lakhs plz. Tell me in p/l account what amount should be debited as construction cost . Whether it is work certified or actual cost incurred. Thanks...!
Replies (3)

as per as 7 in the main P/L ac u directly recognise the profit or loss on the contract and in this case u should recognise a loss of Rs.1.4 lakhs.

 

AS-7 and principal of conservatism says that " you should provide for loss of Rs. 2.00 lacs and thus total cost recognised should be Rs. 5.00 lacs plus Rs. 2.00 lacs i.e, Rs. 7.00 lacs thanks
Thanks sir.! But i want to know the the exact amount to be recognise as current years revenue based on percentage completion method . Is there no effect of work certified on this ?


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
Featured 13 April 2026
GST CONSULTANCY

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
Accountant

Ashok Amol & Associates

New Delhi

B.Com

View Details
Company
Featured 29 April 2026
Manager- Finance and Compliance

Naveen Fintech Pvt Ltd

Kolkata

CA Inter

View Details
Company
Featured 02 May 2026
Senior Executive

hitesh chandwani & co

Pune

B.Com

View Details
Company
Featured 14 April 2026
GST CONSULTANT

Abhishek G Agrawal & Co.

Korba

CA Final

View Details
Company
Featured 28 March 2026
CA Final

Ashok Amol & Associates

New Delhi

CA Final

View Details