Material costing
Arun (Student CA Final ) (142 Points)
01 April 2013Arun (Student CA Final ) (142 Points)
01 April 2013
Originally posted by : Arun | ||
![]() |
From the following records regarding material calculate 1. the re-order level 2. the maximum stock level 3. minimum stock level Re-order quantity : 6000 units Minimum stock ( for emergency) : 5 weeks average delivery time: 4 weeks maximm stock level: 20 weeks average Comsumption per weeks : 400 units Minimum comsumption in 4 weeks : 1200 units. |
![]() |
Arunji, can you please clarify the highlighted text.., its confusing..
Thanks..