CS PURSUING
43853 Points
Joined December 2009
AS PER PARA 5.3.1 OF HAND BOOK OF PROCEDURES VOL-1(2009-2014) "(a) Authorization holder shall produce to the concerned RA a certificate from the Jurisdictional Central Excise Authority, confirming installation of Capital Goods at factory/ premises of authorization holder or his supporting manufacturer(s) /vendor(s) within six months from date of completion of import. (b) In the case of import of spares, the installation certificate shall be submitted by the Authorization holder within a period of three years from the date of import. (c) However, in case of units not registered with Central Excise Authorities, the Authorization holder shall produce to the concerned RA, a certificate from an independent Chartered Engineer confirming the said installation of Capital goods/spares. AFTER Read more: Chapter 5 of the Handbook of Procedures (Volume I) 2009
AFTER REDEMPTION THEY SUBMIT THE DETAIL OF EXPORT FULFILLMENT IN CONCERNED REGIONAL LICENSING AUTHORITY.