Treatment of survey cost

Indian Accounting Standards 675 views 1 replies

Our company is planning to lay Pipeline Project for Joining 3-4 Gas wells. Rout Survey for the same was intially done 5-6 years back and till date project could not be started due to Negative FR.

 

Just want to know whether this intial survey  expenditures should be kept in CWIP(Capital Work in Prog) or should be charged Off. ( I tried to search in AS -10 but couldn't fint anything abt Survey Cost)

Thanks & Regards

anil Chauhan

Dehradun

 

Replies (1)

Dear friend, since the report was negative there was no need to capitalize it.

Now you can charge it in P& L a/c as per AS-5 fue to change in estimation as a seperate item. However, under I.T act you will not be allowed deduction of this expense now


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Related Topics
Loading
Company
ARTICLESHIP 27 May 2026
CA Article Trainee

Rahul Dang & Associates-Chartered Accountants

Pune

CA Inter

View Details
Company
ARTICLESHIP 31 May 2026
Article Assistant

KPRS And Associates

New Delhi

CA Inter

View Details
Company
27 May 2026
Audit Assitant

Virender K Gupta and Co

New Delhi

B.Com

View Details
Company
Featured 27 May 2026
Lead Conversion Executive / Sales Closing Executive

SMJ global advisors pvt ltd

New Delhi

B.Com

View Details
Company
10 June 2026
Senior Account Executive

JDS Advisory LLP

Ahmedabad

CA Inter

View Details
Company
01 June 2026
Audit, Taxation & Compliance Executive

R P S K & Associates

Nashik

CA Inter

View Details
Company
Featured 28 May 2026
SEMI QUALIFIED/ CA DROPOUTS/ ARTICLES

T R SOOD & CO

New Delhi

CA Inter

View Details
Company
09 June 2026
Accounts Associate

S Madan and CO

New Delhi

Graduate (Any)

View Details